In early 2024, a historical structure at a major utility on the U.S. West Coast faced a challenge within its infrastructure. Four 36-inch ball valves needed replacing and required adaptation to fit an old 34-inch line.
Also mandated was the development of the foundation to support the valves at a horizontal incline. Additionally, the requirements needed to be completed within a nine-month time frame, as an outage at the utility was scheduled for October 2024.